Current Projects

Look here to find information on current projects happening in our community to enhance your water service. 

"Subscribe" and receive updates on our Current Projects the minute they are posted.  It's easy!

Contract 1 - Wells

The wells are getting fitted for pumps.

Water Treatment Plant after Hurricane Laura

We did receive a small amount of damage from Hurricane Laura.  Peck Construction was onsite the next day making repairs.  We do not think this will delay the project.

Riverton Water Treatment Plant

The treatment plant is moving along.  The ground storage tank is up and the treatment building is going up.  We anticipate the treatment plant being up and inline working by early 2021.

Water System Improvement Contract #2 - New Water Treatment Plant

If you see red flags around your meter please do not remove.  These flags are being used to mark the existing meters that are being replaced with radio read meters.

Construction to begin on new water treatment plant located in Riverton, LA.

Replace 4" line with 6" line on Hwy 4 East

Install radio read meters

Water System Improvement Contract #1 - Riverton Wells (2)

Due to COVID19 the drilling contractor has suspended work.

New construction begins on two new wells located in Riverton, LA.

Davis Lake Nursery Project (COMPLETED)

Louisiana Department of Health issued our permit on May 06, 2019 to begin working on the Davis Lake Nursery Project.  This is an extension of approximately 2,800 feet of a new 6" water main along Nursery Road, several water meters and two fire hydrants.

Work is currently scheduled to begin the last week of May.

Subscribe to Stay Informed!

Working harder to better serve and communicate with our community we have launched a new website for our water customers. Check it out and let us know what you think. Subscribe today!